Case Study: Doing the Studies Out of Order

What the City Actually Did

The City did the opposite order — compensation first, organizational structure second, roughly three years later:

Step State Auditor’s Order City’s Actual Order Date
1 Organizational structure study (not done until 2025) Target: September 2021
2 Staffing/duties analysis (not done until 2025, bundled into the Citygate study) Target: after Step 1
3 Compensation study Compensation study — done first Council approved contract with Koff & Associates: July 19, 2022. Work began August 31, 2022.
— — Service Delivery (organizational) study — done second, ~3 years later Contract executed with Citygate Associates: July 29, 2025

Koff contract approval and start dates: El Cerrito CAP Progress Report, March 2023.pdf, Executive Summary — “The City Council approved a contract with Koff and Associates for a Citywide classification/compensation study on July 19, 2022. Koff and Associates began their work as of August 31, 2022.” Citygate contract date: CITYGATE ASSOCIATES, LLC 2025.7.29-1.pdf and CITYGATE ASSOCIATES LLC Amendment 20260630.pdf, Recital A — “On July 29, 2025, City and Consultant entered that certain Consulting Services Agreement…”

The gap this created: the compensation study (delivered ~February 2024, per prior analysis) compared El Cerrito’s pay to other cities’ pay for positions whose duties, structure, and staffing levels had never been independently analyzed — the exact analysis the Auditor said should happen first, specifically so that “overlapping areas of responsibility and inefficiencies” could be identified before, not after, salaries were benchmarked against other cities.

Timing Context

  • The State Auditor’s target date for the first step (organizational structure) was September 2021.
  • The City did not contract for that study until July 29, 2025 — approximately four years after the Auditor’s target date, and three years after the compensation study had already been completed.
  • The City’s own March 2022 and March 2023 Corrective Action Plan updates continued to report the classification/compensation study as “in process,” without independently flagging that it was proceeding out of the Auditor’s recommended sequence.

The City’s Later Reframing

By March 2023, the City’s own progress report began pushing back on the substance of Issue #4 itself, rather than addressing the sequencing:

“The City believes the criteria and recommendations in this risk area results in the City being judged for conditions that no longer exist and cannot be sustained… Unlike the original speculation by the State Auditor team that the classification and compensation study would provide areas of efficiency and cost savings, it is now understood that the study will instead highlight how far behind the market many of the City’s positions are.”

Source: El Cerrito CAP Progress Report, March 2023.pdf, Executive Summary.

This reframing — from “we agree and will follow this sequence” (2021) to “this risk area no longer applies” (2023) — happened without the organizational structure study (the Auditor’s actual first-step recommendation) ever having been conducted. The City did not commission that study until more than two years after this reframing.

See Service Delivery Study and Compensation Study for the detailed record of each individual study.